What you need

  • Spot levels on a grid: here a 20 m × 20 m plot surveyed every 10 m, nine levels. Columns A, B, C run east, rows 1, 2, 3 run north, so A1 is the south-west corner.
Row A B C
3 (north) 24.600 25.050 25.500
2 24.300 24.800 25.200
1 (south) 24.100 24.450 24.900
  • The formation level: the level the plot is to be brought to. Here a flat formation at 24.700.

Step 1: the depth at every node

At each node, depth = ground − formation. A positive depth is cut (ground to come off), a negative depth is fill (ground to make up).

Row A B C
3 −0.10 +0.35 +0.80
2 −0.40 +0.10 +0.50
1 −0.60 −0.25 +0.20

Step 2: cut and fill, cell by cell

Each 10 m × 10 m cell (area A = 100 m²) has a depth at its four corners. With Σh⁺ the sum of the positive depths and Σh⁻ the sum of the negative ones (as sizes):

  • All cut: cut = A × Σh⁺ ÷ 4
  • All fill: fill = A × Σh⁻ ÷ 4
  • Both (the four-point formula): cut = A × (Σh⁺)² ÷ (4 × (Σh⁺ + Σh⁻)), fill = A × (Σh⁻)² ÷ (4 × (Σh⁺ + Σh⁻))
Cell Corners Σh⁺ Σh⁻ Cut (m³) Fill (m³)
1 (A1–B2) −0.60, −0.25, +0.10, −0.40 0.10 1.25 0.19 28.94
2 (B1–C2) −0.25, +0.20, +0.50, +0.10 0.80 0.25 15.24 1.49
3 (A2–B3) −0.40, +0.10, +0.35, −0.10 0.45 0.50 5.33 6.58
4 (B2–C3) +0.10, +0.50, +0.80, +0.35 1.75 0 43.75 0
Total 64.50 37.00

Cell 1, for example: cut = 100 × 0.10² ÷ (4 × 1.35) = 0.19 m³, fill = 100 × 1.25² ÷ (4 × 1.35) = 28.94 m³.

At 24.700 there is 27.50 m³ more cut than fill: earth to be carted away.

Step 3: the balancing level

The formation at which cut equals fill is the mean level of the ground. By the grid method, each node’s level counts once for every cell it belongs to: corner nodes once, edge nodes twice, the centre node four times.

  • Corners: 24.100 + 24.900 + 24.600 + 25.500 = 99.100
  • Edges, twice: 2 × (24.450 + 24.300 + 25.200 + 25.050) = 198.000
  • Centre, four times: 4 × 24.800 = 99.200
  • Mean = (99.100 + 198.000 + 99.200) ÷ 16 = 24.769

A formation of about 24.77 levels the plot with no earth brought in or taken away.

The TIN method

Survey software joins the surveyed points into triangles (a TIN) and takes the ground as flat inside each triangle. Then each triangle gives an exact volume: area × the mean of its three corner depths when it is all cut or all fill. A triangle that has both is split along the line where the depth is zero (the zero line) and each part is worked out the same way.

Take cell 4, all cut, split corner to corner into two triangles of 50 m²:

  • B2, C2, C3: 50 × (0.10 + 0.50 + 0.80) ÷ 3 = 23.33 m³
  • B2, C3, B3: 50 × (0.10 + 0.80 + 0.35) ÷ 3 = 20.83 m³
  • Cell 4 by TIN: 44.17 m³, against 43.75 m³ by the grid

Over the whole plot, split this way, the TIN gives cut 65.17 m³ and fill 36.84 m³. The grid figures are 1.0% lower for the cut and 0.4% higher for the fill. The TIN’s balancing level, the area-weighted mean of the triangles, comes to 24.771.

(These figures were worked with the same formulas CivilSurvey Expert uses, and checked by calculation.)

Why the two figures differ, and which to report

  • The grid knows only the corners. It treats the ground inside each cell by a formula. The TIN follows every triangle, so a bank or a drain between grid nodes is in the TIN and not in the grid.
  • Cells crossed by the zero line are approximated by the four-point formula. The TIN finds the zero line itself.
  • Cells cut by the boundary use corner depths that may lie outside the plot.

On real survey data the TIN is built on the actual surveyed points, not on a grid, so it is exact for the surveyed surface. Report the TIN figure and keep the grid statement as the check a checker can follow by hand: a finer grid comes closer to it. If the two differ by more than a few per cent, use a finer grid, or look for ground the grid is missing.

Things to watch

  • A fall for drainage. With a sloping formation, use the formation level at each node, not one level for the plot, before taking the depths.
  • The boundary. Work out only what is inside the plot. Ground outside it is not your earthwork.
  • Factors. These are volumes of ground as it lies. Apply your department’s bulking or compaction factors separately, as the estimate requires.

The same surface gives the contours too: see how to draw contours from total station data.